Logistics Centre – Technical Assessment
All Projects

Commercial / Existing Stock

Logistics Centre – Technical Assessment

Full technical assessment of a large-scale logistics complex in Hesse, including high-bay warehouse with 23 m clear height. Three remediation scenarios evaluated, investment volumes €9M–€15M.

Commissioned by an institutional property investor, we carried out a comprehensive technical assessment of a large logistics facility in Hesse, Germany — fully let and in active operation.

The complex comprises five interconnected warehouse halls totalling approx. 35,600 m², including a high-bay racking hall (HRL) of approximately 23 m clear height, built in 1999. Two critical deficiencies required immediate action: a structurally unstable façade and significant fire-protection shortfalls.

We analysed two existing remediation scenarios and independently developed a third. Each option was assessed across cost, technical complexity, compliance, tenant impact, and long-term asset value. Investment volumes ranged from approx. €9M to €15M net.

The assignment resulted in a 23-page decision-ready report with detailed cost projections for all three scenarios. Our primary recommendation — façade demolition and roof lowering — was accepted as the strategically and economically optimal path forward.

Location

Bad Hersfeld, Hesse, Deutschland

Year

2025

Area

approx. 35,600 m² GFA

Team

Aiko Domke (with ESTATA GmbH)

Phases

Technical Due Diligence / Cost Assessment

Logistics Centre – Technical Assessment 1
Logistics Centre – Technical Assessment 2
Logistics Centre – Technical Assessment 3

Let's Talk

Let's talk about your investment

Every advisory relationship starts with a conversation. Tell us about your project — we'll take it from there.